Info to date:
·      We are yet (8/02/11) to get clearance for adults to be on site at school.
·      A Level 2 structural engineers report has been commissioned by the MoE after our initial report identified some areas needing reviewed.
·      Our project manager has already organized a builder to come in and carry out a number of remedial repairs.  Lights & heaters have been reconnected to our ceilings, racked doors realigned, broken windows repaired.
·      Liquefaction has been cleared from the site
·      1000 liter Water tank of clean purified drinkable water delivered to school on 9/02/11
·      MoE sourcing portaloos as back up if sewerage system not operating when school returns.

 Where to next:
·      Once a structural engineering report is forwarded to the MoE that indicates our premises are safe I can complete an application to the MoE for ADULTS to be onsite.
·      We then need staff to come in and assist in the clean up
·      Cracked windows need to be taped, liquefaction residue cleaned and full internal clean.
·      Drink fountains to be turned off by plumber prior to students returning.
·      Assessing staff personal situations, availability, state of mind and ability to fulfill their responsibilities to students.
·      Complete reopening plan.