W O O L S T O N R E O P E N I N G P L A N S
Info to date:
· We are yet (8/02/11) to get clearance for adults to be on site at school.
· A Level 2 structural engineers report has been commissioned by the MoE after our initial report identified some areas needing reviewed.
· Our project manager has already organized a builder to come in and carry out a number of remedial repairs. Lights & heaters have been reconnected to our ceilings, racked doors realigned, broken windows repaired.
· Liquefaction has been cleared from the site
· 1000 liter Water tank of clean purified drinkable water delivered to school on 9/02/11
· MoE sourcing portaloos as back up if sewerage system not operating when school returns.
Where to next:
· Once a structural engineering report is forwarded to the MoE that indicates our premises are safe I can complete an application to the MoE for ADULTS to be onsite.
· We then need staff to come in and assist in the clean up
· Cracked windows need to be taped, liquefaction residue cleaned and full internal clean.
· Drink fountains to be turned off by plumber prior to students returning.
· Assessing staff personal situations, availability, state of mind and ability to fulfill their responsibilities to students.
· Complete reopening plan.